Also called: production schedule, stripboard, shoot schedule
A shooting schedule orders every scene of a script into shooting days, grouped by location, cast availability and day or night rather than by story order. Built by the first assistant director from the script breakdown, it decides how many days the film needs and becomes the backbone of the budget and every call sheet.
- What it does
- Turns a script into a day-by-day plan that shoots each location once and keeps actors on the payroll as few days as possible.
- Use it when
- Any shoot longer than a single day, from a two-day short to a sixty-day feature.
- Watch out
- Packing too many pages into one day; the schedule looks efficient on paper and collapses by lunch on day three.
- Try this prompt
Plan it on the board: one column per shooting day, storyboard frames grouped by set, cast IDs and page count noted under each column
What is a shooting schedule?
A shooting schedule is the plan that tells a production which scenes it will shoot on which day, in which order, at which location, with which actors. It is written during pre-production, after the script breakdown has tagged every scene with its elements: cast, extras, props, vehicles, stunts, effects, set.
Each scene becomes one entry (on paper, a strip) carrying the scene number, INT or EXT, day or night, the set name, a one-sentence description, the page count in eighths of a page and the cast ID numbers. The first AD then arranges those entries into shooting days, adds day breaks and company moves, and prints the full schedule and the short one-liner.
On a feature the schedule is one of the key documents of the filmmaking process: the line producer budgets from it, department heads plan prep from it, and the 2nd AD builds each day's call sheet from it.
Why are films shot out of order?
Because story order is the most expensive order there is. A script might return to the same kitchen in scenes 4, 31 and 88; shooting them on three separate weeks means lighting and dressing that room three times and paying for three company moves. Grouping them into one day costs a costume change and some continuity notes.
The scheduler weighs, roughly in this order:
- Location. Shoot everything at one place before moving. A company move eats one to three hours of a working day.
- Cast. An actor who works days 2 and 19 is often paid to hold in between. The Day Out of Days report shows those gaps so scenes can be pulled together.
- Day and night. Night work is slow and forces turnaround: cast and crew need their rest period (commonly ten to twelve hours, depending on the agreement) before the next call. Schedules move from days to nights across a week rather than flipping back and forth.
- Constraints. Child actors' limited hours, animals, stunts, weather, special effects rigs, a location that is only free on Sundays.
The cost of ignoring this is visible in The Revenant (2015). Alejandro G. Iñárritu chose to shoot largely in story order and in natural light, which stretched the schedule and, when the snow in Canada ran out, sent the production to Argentina to finish the ending. Directors sometimes pay that price for performance; most productions cannot.
How to make a shooting schedule
- Lock and number the scenes. Otherwise every revision means starting over.
- Break it down. One breakdown sheet per scene, every element tagged. Measure each scene in eighths of a page; a scene of one and a quarter pages is 1 2/8.
- Make the strips. The common color code is white for INT day, yellow for EXT day, blue for INT night, green for EXT night, so the board shows the day-night rhythm at a glance.
- Group by location, then by cast. Cluster every strip for one set, then order within the set so each actor's days are contiguous.
- Set a pace. Decide pages per day from the budget and the style of the film. A dialogue scene in two chairs moves fast; an eighth of a page that reads "they fight across the roof" can take a full day. Estimate setups, not just pages: check the shot list for each scene.
- Place the hard things well. Don't open on the most demanding scene; give the crew a day or two to find its rhythm. Put exteriors early in the schedule and keep an interior cover set ready for bad weather. Schedule emotional peaks when the actors are fresh, not at hour eleven.
- Insert day breaks and check the totals. Count days, pages and cast days, compare with the budget, then cut, combine or move scenes until they agree.
The stripboard and the boneyard
Before software, a schedule lived on a stripboard: a folding frame of long cardboard strips, one per scene, color-coded and printed with scene data. Rearranging the shoot meant sliding strips around; a black strip marked the end of each shooting day. Digital schedulers still draw the same board.
The boneyard is the parking area of that board. Strips that are not yet assigned to a day go there: scenes cut from the script, scenes waiting on a location or an actor's dates, pickups that may or may not happen. Keeping them in the boneyard instead of deleting them preserves their breakdown data, so a scene can come back into the schedule without being rebuilt.
What is a one-line schedule?
The one-line schedule, or one-liner, is the condensed printout of the shooting schedule. Each scene takes a single line: scene number, set, INT or EXT, day or night, page count and cast IDs, grouped under a header for each shooting day with the day's page total.
It is the version most of the crew actually carries. The director and DP read it to see the shape of the shoot; department heads use it to spot their busy days; the 2nd AD pulls tomorrow's scenes from it. Props, extras and special equipment stay in the full schedule.
Shooting schedule vs. production timeline
A production timeline covers the life of the whole project: development, prep, shoot, post and delivery, with milestones such as picture lock and the first festival deadline. The shooting schedule covers only the shoot itself, but at the level of individual scenes and days. The timeline says "principal photography, six weeks from March 3"; the schedule says what happens on each of those thirty days.
The call sheet sits one level lower: one day of the schedule, expanded with call times, addresses and safety notes.
Planning the shoot visually
A schedule is a spreadsheet, but the choices behind it are visual: which scenes share a set, which need the same light, where the night work falls. On a FlashBoards board you can lay out storyboard frames and reference stills in columns by shooting day instead of by scene number, with notes on cast and setups under each column. When the director asks to move a scene, everyone sees what else shares that set and that light before the strip moves.
Keep the reference frames, prompts and every generated take side by side — images and video in one canvas.
FAQ
5 questionsWhat is a shooting schedule in film?
A shooting schedule is the document that assigns every scene of a script to a specific shooting day. Scenes are grouped by location, cast availability and day or night rather than story order, to save time and money. The first assistant director builds it from the script breakdown, and it drives the budget, the cast deals and each day's call sheet.
Who makes the shooting schedule?
The first assistant director, working from the script breakdown with the director, the line producer or production manager and the heads of department. A producer may draft a preliminary schedule early to estimate the budget; the first AD refines it during prep and keeps updating it through the shoot.
How many pages of script can you shoot in a day?
It depends on the budget, the style and the content. Large features often shoot two to four pages a day, low-budget features five or more, and some television formats move faster still. Page count is only a proxy: count setups, stunts, effects and company moves, because a short action scene can take longer than several pages of dialogue.
What is the difference between a stripboard and a shooting schedule?
The stripboard is the working tool; the shooting schedule is its result. A stripboard shows each scene as a color-coded strip that can be rearranged into days, with day breaks between them and a boneyard for unassigned scenes. Once the arrangement works, it is printed as the shooting schedule and the one-line schedule.
Is a shooting schedule the same as a production schedule?
People often use the terms interchangeably. Strictly, the shooting schedule covers only principal photography, scene by scene and day by day. A production schedule or production timeline can mean the wider calendar of the whole project, from prep through post-production and delivery, where the shoot is just one block.
Related terms
3- Call SheetFilmmaking Process & Crew
A call sheet is the daily document sent to cast and crew the night before a shoot, listing call times, scenes, locations, weather, contacts and safety notes for that day; it is usually prepared by the 2nd AD.
- Script BreakdownFilmmaking Process & Crew
A script breakdown goes through the screenplay scene by scene and tags every production element — cast, extras, props, wardrobe, vehicles, effects, locations — so it can be budgeted and scheduled.
- Pre-ProductionFilmmaking Process & Crew
Pre-production is the planning phase between greenlight and the first shoot day: casting, crewing, location scouting, design, storyboards and shot lists, breakdown, schedule and budget are locked here.
Further reading
Maureen Ryan, Producer to Producer (Michael Wiese Productions). Ralph S. Singleton, Film Scheduling (Lone Eagle).